NHDOT Route 1A Coastal Revetment Improvements

Project 42312 Little Boar’s Head | North Hampton & Rye
NHDOT Project 42312 Seawall Sections

Little Boar’s Head District Impact

NHDOT is advancing Project 42312 to reconstruct coastal revetments (seawalls) along NH Route 1A. Portions of the work occur within Little Boar’s Head (Sections 10 and 13).

  • Location: Ocean Boulevard (Sections 10 & 13)
  • Work: Rebuild existing seawalls
  • Design Standard: 2050 storm conditions
  • Alignment: Same roadway alignment and crest elevation as 1978 footprint

No expansion into new areas.
No extension further into the Historic District.
No archaeological impacts identified.

Project maps are included in the Historic Review letter below.


Historic Review

View Letter Here

Determination: No Historic Properties Affected

The NH Division of Historical Resources concurred with this finding.


Design & Coordination

View Memo Here

Construction (Anticipated)

NHDOT42312CauseswayStagingAreaOne-lane alternating traffic

Off-peak months (October–April)

Proposed temporary closure of part of Causeway Road during Section 10 work

Property access maintained

Sidewalks

Sidewalks included in project

ADA compliant

Municipal maintenance agreement under discussion


Updates