SECTION 6 - ADDITIONAL PERMIT REQUIREMENTS
6.1 Size and Reclamation Time Limit on New Excavation
No excavation of a new area shall exceed five acres in size at any one time. Any permitted excavation shall be reclaimed according to the approved application within one (1) year after the permit expiration date. If reclamation of the site is not completed within one (1) year after the permit expiration date, the Town may declare part of all of the bond forfeited, and use these monies to reclaim the site, in addition to the requirements of Section 13 (Issuance of Permit).
6.2 Additional Conditions
In accordance with Section 9, Prohibited Projects, the Regulator may attach reasonable conditions to permit approval. Such conditions may include, but not be limited to, the following.
6.2.1 the applicant shall be responsible for a proportionate share of refurbishing existing Town road(s) which access the excavation site, and for the repair of Town maintained roads which are damaged as a result of hauling earth from the site. The Regulator may require these costs to be bonded prior to the granting of a permit to excavate.
6.2.2 no solid and/or hazardous waste, septage, dredge spoils, or organic waste and debris shall be disposed of on the excavation site unless specifically authorized and/or permitted by the appropriate Federal, State and local authorities.
|